Construction Gallery |
|
September 2005: |

13/09/05: Inside the workshop a seat frame is constructed. |
|
|
October 2005: |

17/10/05: The hub and arms are put together outside the workshop. |

18/10/05: You can see the height of the tower next to Scorpion. |
|
November 2005: |

07/11/05: The tower and platform are being temporarily built up behind the Go Karts. |

10/11/05: The skeleton of the platform can be seen, now with a fence added. |

12/11/05: Seats for the ride have arrived in the park's truck. |

28/11/05: Work continuing on the central hub. |

28/11/05: A shot of the ride's centre section. |
|
|
December 2005: |

01/12/05: Seat frames have been primed / painted. |

01/12/05: Top-down shot of the tower. |

03/12/05: The centre section. |

03/12/05: Some painted arms and primed seats. |

07/12/05: Shiny steel frame sections. |
|
|
January 2006: |

14/01/06: The tower and hub outside the workshop. |

21/01/06: This is where the seat will join the arm. |

21/01/06: These pink bits of steel will suport the ride's platform. |

31/01/06: Vertical construction! |

31/01/06: The first arm is attached. |

31/01/06: And the second. |

31/01/06: Arms sit ready to be lifted on to the ride structure. |

31/01/06: Another arm on its way up. |

31/01/06: Hanging in mid air. |

31/01/06: The arm joins the rest of the ride. |

31/01/06: The ride now with three arms in place. |

31/01/06: The process continues until all eight arms are attached. |
|
February 2006: |

01/02/06: An overview of the site. |

01/02/06: And another. |

01/02/06: A look at the first seats in place. |

01/02/06: Another look at the seats at the bottom of the structure. |

04/02/06: This pic shows the height. |

04/02/06: The progress so far. |

07/02/06: Seats sitting next to the Scorpion ready to be attached. |

09/02/06: The current look of the ride. |

09/02/06: The control box, fences and a hydraulic system to help with loading are all in. |

09/02/06: Work on the electrics of the ride. |

11/02/06: This panel will be at the bottom of the tower. |

12/02/06: The ride's signs have been created by Art & Design. |

25/02/06: Fireball theming added. |

25/02/06: Another shot of the Fireball theming. |

25/02/06: The queueline is being constructed. |

25/02/06: Work on the queueline. |